Radiogram 0485u Form 24 for 06/12/09
CREW OFF DUTY
GMT CREW ACTIVITY
06:00-06:10 CDR, FE-3,FE-4, FE-5 Morning inspection
06:00-06:05 FE-1, FE-2 SLEEP data logging
06:05-06:10 FE-1, FE-2 Morning inspection
06:10-06:40 CDR, FE-1,FE-3, FE-4
06:10-06:45 FE-2 Post-sleep
06:10-06:50 FE-5
06:40-07:30 CDR, FE-1,FE-3, FE-4 BREAKFAST
06:45-07:00 FE-2 Private family conference (Ku+S-band)
06:50-06:55 FE-5 HAM radio equipment prep
06:55-07:05 FE-5 HAM radio comm. Session
07:00-07:30 FE-2 BREAKFAST
07:05-07:45 FE-5 BREAKFAST
07:30-07:50 FE-2 Crew preference activity (Ku+S-band)
07:50-08:00 FE-2 BREAKFAST
08:00-09:30 FE-5 Physical Exercise (ARED)
08:15-08:25 FE-3 Checking for coolant leak on the КОБ2 4ГБ4 half-coupling shell
08:30-09:30 FE-4 Physical Exercise (CEVIS)
09:00-09:20 FE-2 Crew preference activity (Ku+S-band)
09:30-10:30 FE-5 Physical Exercise (CEVIS)
09:30-09:45 CDR, FE-3 Telephone conference with the editor of Rossiyskiy Kosmos (Russian Space) magazine (S-band)
09:35-10:50 FE-2 Physical Exercise (ARED)
10:00-10:30 FE-1 BIORHYTHM: data downlink
10:30-11:30 FE-1 Physical Exercise (CEVIS)
10:40-11:40 FE-3 Physical Exercise (ARED), day 2
10:50-12:05 FE-2 Physical Exercise (TVIS)
10:50-11:00 CDR Complete discharge of 1st 825М3 unit of Orlan and start 2nd unit No. 1268990195 (b/c 00044937) discharge
11:30-12:30 CDR Physical Exercise (VELO), day 2
11:30-13:00 FE-1 Physical Exercise (ARED)
11:35-11:40 FE-5 HAM radio equipment prep
11:40-11:50 FE-5 HAM radio comm. session
12:30-13:00 CDR Hygiene procedures
12:30-12:45 FE-3 Private family conference (Ku+S-band)
12:35-12:40 FE-4 ALTEA: dosimeter equipment deactivation
12:45-13:00 FE-4 Food questionnaire
12:55-13:00 FE-3 On MCC Go ISS repress using Progress СРПК (start)
13:00-14:00 . LUNCH
14:00-14:30 FE-4 Psychological assessment program (WinSCAT)
14:00-14:05 FE-3 ISS repress using Progress СРПК (terminate)
14:00-14:55 FE-5 Н2 sensor removal
14:05-14:45 FE-3 СОЖ maintenance
14:30-15:30 FE-4 CGSE packing
14:40-15:10 FE-1 Psychological assessment program (WinSCAT)
15:00-15:10 FE-2 BSA battery charge term.
15:10-15:20 FE-1 PAO equipment setup
15:10-15:20 FE-2 EMU: REBA charge term.
15:20-15:30 FE-1 Crew prep for PAO
15:20-16:20 FE-2 PGT checkout
15:30-16:30 CDR Physical Exercise (ARED), day 2
15:30-15:50 FE-1 PAO event (S-band)
15:40-15:50 FE-4 ALTEA: dosimeter equipment activation
15:50-16:00 FE-1 PAO equipment deactivation
16:20-16:50 FE-2 Reboot all PCS/PWS
17:00-17:20 CDR, FE-4, FE-5 ESA weekly crew conference (S-band)
18:00-18:05 FE-2 ELT laptop deactivation
18:00-19:00 FE-3 Physical Exercise (VELO), day 2
18:00-19:30 FE-4 Physical Exercise (ARED)
18:15-18:20 FE-1 ОСА SSC router reboot
18:20-18:25 FE-1 SSC file server reboot
18:20-18:35 FE-5 Food questionnaire
18:35-19:05 FE-5 Psychological assessment program (WinSCAT)
19:00-19:30 FE-3 Hygiene procedures
19:25-19:30 FE-2 TVIS, CEVIS, and HRM data transfer to MEC
19:30-20:50 CDR, FE-3 Pre-sleep (dinner, daily food prep, evening toilet)
19:30-21:30 FE-1, FE-2,FE-4, FE-5 Pre-sleep (dinner, daily food prep, evening toilet)
20:50-21:00 CDR, FE-3 Conference with Tall ships Atlantic Challenge 2009 participants (S-band)
21:00-21:30 CDR, FE-3 Pre-sleep
21:30-06:00CDR, FE-2, FE-3,FE-4, FE-5SLEEP
21:30-23:35 FE-1 SLEEP
23:35-23:50 FE-1 Private family conference (S-band)
23:50-06:00 FE-1 SLEEP
Task List
CDR, FE-3 Urine transfer from ЕДВ-У into Rodnik tank of Progress No. 402
CDR URAGAN. Observation and imaging
CDR EKON. Observation and imaging
Notes:
1. Window No. 9 shutter opening is at crew discretion with Report to MCC
2. See OSTP for references to US activities
End of radiogram